DCAN 10: Environmental Impact Assessment

16.1 Where a planning application requires to be accompanied by an Environmental Statement, the period within which a decision shall be made is extended to 16 weeks from the date of receipt of the application including the ES.

16.2 If such an application is designated as major under Article 31 of the Planning (Northern Ireland) Order 1991, the designation must also be made within 16 weeks of the receipt of the application including the ES.

16.3 Appeals for non-determination of EIA applications cannot therefore be made until after 16 weeks from the date of receipt of the ES.