61. The Department will normally require developers to bear the costs of works required to facilitate their development proposals. Contributions may be required in a variety of circumstances including:
  • where a proposed development requires the provision or improvement of infrastructural works over and above those programmed in development plans;
  • where earlier than planned implementation of a programmed scheme is required;
  • where a proposed development is dependent upon the carrying out of works outside the site.