Housing Zoning BYH 26
Nursery, Route Avenue (0.38 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per
hectare.
2. The development of this site will require additional lands to provide
an access
to Knock Road via Route Avenue, which shall be upgraded to a
satisfactory
standard. This may necessitate acquiring control over land
outside the
boundary of the site.
3. Footpath links shall be provided to the existing network
4. The development of this site will require substantial improvements to
means
of storm water disposal, with consequent potential costs to
the developer.
|
Housing Zoning BYH 27
Land opposite 4 Park Lane (0.15 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare and
be in keeping with neighbouring dwellings in Park Lane.
2. Access to this site shall be from Park Lane.
|
Housing Zoning BYH 28
Land to rear of 2-6 Cambourne Drive (0.62 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. The development of this site may require additional lands to provide an
access
to Bann Road.
3. A footpath shall be provided to link to the existing network.
4. The existing boundary hedge shall be retained.
|
Housing Zoning BYH 29
Land south west of Seymour Drive (0.73 ha.)
|
Key Site Requirements
1. Development shall be within the range of 25 to 35 dwellings per hectare.
2. The development of this site will require additional lands to provide an
access
to Seymour Drive.
3. Dwellings shall be orientated towards the open space area to the north.
4. Footpath links shall be provided to the existing network
5. Any development proposal shall identify all trees worthy of retention and
ensure that no activity, works or storage takes place within the limit of the
crown spread of the trees, or a distance of half the height of the trees,
whichever is the greater.
6. Development may require noise attenuation measures because of its proximity
to the Belfast to Londonderry railway line.
|
Housing Zoning BYH 30
Lands east of Westoncroft Ave. (0.76 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. The access to this site shall be shall be on to Westoncroft Avenue.
3. A right turn facility may be required at the junction of Ishlan Court and
Charlotte Street.
4. The junction of Ishlan Court and Charlotte Street may require to be
upgraded.
To ensure compliance with the appropriate Departmental standards
additional
lands may be required.
5. Any development proposal shall identify all trees worthy of retention and
ensure that no activity, works or storage takes place within the limit of the
crown spread of the trees, or a distance of half the height of the trees,
whichever is the greater.
6. A pedestrian/cycle way shall be provided through this site linking
Westoncroft
Avenue to the town centre via Shiel’s Court.
|
Housing Zoning BYH 31
Lands north east of Greenhill Dr. (1.90 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. Additional lands will be required to provide an access to this site from a
public
road. It may be possible to gain access from Semicock Road via the lane
adjacent to part of the site or through Queens Avenue. A further option may
be
to combine this site with BYH 17 and take an access onto Knock Road.
3. The development of this site will require substantial improvements to storm
water drainage, with consequent potential costs to the developer.
|
Housing Zoning BYH 32
Lands south of Claire’s Hill (0.65 ha.)
|
Key Site Requirements
1. Development shall be within the range of 10 to 15 dwellings per hectare.
2. Access constraints will limit the number of dwellings which can be
accommodated on this site. Shared private access shall be via one or
both of the existing laneways which may require to be upgraded
depending on the number of dwellings approved onto each lane from Kirk
Road.
3. Development on the site shall be single storey only.
4. Additional lands may be required to provide an access or accesses on to
Kirk
Road.
5. A 2.0m wide footway shall be provided along the frontage of the site and
linked to the existing network.
6. The mature trees within and on the periphery of the site shall be retained.
Only those required for construction of an access way shall be removed.
7. Any development proposal shall identify all trees worthy of retention and
ensure that no activity, works or storage takes place within the limit of the
crown spread of the trees, or a distance of half the height of the trees,
whichever is the greater.
|
Housing Zoning BYH 33
Rear of 2-8 Ballymena Road & 2 and 4 Kilraughts Road (1.02 ha.)
|
Key Site
Requirements
1. Development shall be within the range of 10 to 15 dwellings per hectare.
2. Dwellings shall be orientated towards the Riverside Park and not exceed two
storeys in height.
3. The development of this site may require additional lands to provide an
access
to Kilraughts Road and this should be located towards the eastern end
of the
site frontage.
4. Trees and hedgerows on the periphery of the site shall be retained.
5. Any development proposal shall identify all trees worthy of retention and
ensure that no activity, works or storage takes place within the limit of the
crown spread of the trees, or a distance of half the height of the trees,
whichever is the greater.
6. A bat survey will be necessary.
|
Housing Zoning BYH 34
Lands between 30 & 32 Ballymena Road (3.49 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. The detailed design and layout shall have regard for the character of
adjacent
residential development.
3. Existing trees and hedgerows shall be retained and incorporated into the
development.
4. Dwellings along the eastern side of the site shall be orientated towards
the
informal recreational area.
5. Pedestrian access into the adjacent park shall be provided.
6. Access to this site shall be from Ballymena Road where a right turn
facility
may be required.
7. The access shall be sited to ensure appropriate separation from accesses on
the same side and the opposite side of the road.
8. A footway shall be provided along the frontage of the site and linked to
the
existing network to/from the town.
|
Phase 1 Housing Zonings (Urban Fringe)
The following urban fringe sites are zoned for housing development, subject to
compliance with the key site requirements and other requirements for the
development of each site consistent with relevant planning policy including
current Planning Policy Statements and the specific considerations related to
the submission of planning applications:
Housing Zoning BYH 39
Land to the rear of 57 & 59 Knock Rd. (0.76 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. The access shall be onto Knockeden Avenue.
3. No access will be permitted onto the A26 Frosses Road (Protected Route)
4. Development may require sound attenuation measures to mitigate by-pass
traffic noise.
|
Housing Zoning BYH 40
Land east of Eastburn Dr. (1.55 ha.)
|
Key Site Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. Development may require sound attenuation measures to mitigate by-pass
traffic noise.
3. The access to this site shall be from Greengage Lane.
|
Housing Zoning BYH 41 Land north of Ashlea Place, Kilraghts Rd. (1.69 ha.)
|
Key Site Requirements
1. Development to be within the range of 15 to 25 dwellings per hectare.
2. The access to this site shall be onto Ashlea Drive.
3. No access will be permitted onto the A26 Frosses Road. (Protected Route)
4. Development may require sound attenuation measures in order to mitigate
the twin effects of by-pass traffic noise and rail noise from the Belfast to
Londonderry railway line.
5. A wild-life corridor of native species vegetation shall be planted along
the
boundary with the railway.
|
Phase 2 Housing Zoning
The following site is zoned for housing development, subject to compliance
with the key site requirements and other requirements for the development of
the site consistent with relevant planning policy including current Planning
Policy Statements and the specific considerations related to the submission of
planning applications. The release of this land for development will be
dependent on progress of housing development in the town of Ballymoney and
within the Borough consistent with all of the strategic planning guidance of
the Regional Development Strategy, including the objective of achieving 60% of
housing within the existing urban footprint. It is not envisaged that this
land will be required before the year 2010.
Housing Zoning BYH 42 Lands between Finvoy Rd, Milltown Rd & Bravallen Rd. (11.23 ha.)
|
Key Site
Requirements
1. Development shall be within the range of 15 to 25 dwellings per hectare.
2. The open space provision shall include an area at the northern end of the
site, centred on the Ballymoney River.
3. The layout shall be designed with dwellings facing on to the surrounding
roads.
4. The stream on the eastern side of the site shall be retained as a wild-life
corridor.
5. An acceptable Transport Assessment will be required for this site.
6. Access to this site shall be from Finvoy Road and Bravallen Road. Right
turn lanes will be required at appropriate accesses from these two roads.
7. Footpaths shall be provided along the frontage of the entire site and
linked